A leading wholesale distributor to convenience stores (C-Store channel) required multiple categories reset and remodels, including fixture movement. The retailer, distributor, and vendor did not have the labor capacity to complete the project within the planned execution window.
Solution
The wholesale distributor hired us to build a hard-dated reset schedule. Our team utilized SmartProject® to provide consistent and transparent execution results. We met the deadline set by our client by completing resets and remodels across 175 locations in six weeks. We completed an average of 30 locations per week by delivering 24 person-hours per location.